Charging hubs and dynamic load balancing — group capacity instead of summing per charge point
Charging hubs and dynamic load balancing — group capacity instead of summing per charge point
The 722-ev-charging guide covers the installation requirements for an individual charge point: earthing system, RCD type, cable cross-section. This article covers what changes once multiple charge points are combined on a single connection — a charging hub at an office, apartment complex or business park — and why the connection capacity is then not simply the sum of all charge points at full power.
The problem: summing at full power is unnecessarily heavy
A charging hub with, say, ten charge points of 11 kW each would, if the connection were sized for the sum of all charge points at full power simultaneously, require a connection capacity of 110 kW. In practice, rarely do all vehicles charge simultaneously at full power — most charging sessions only partially overlap, and many users do not need full power to charge sufficiently within the available time. A connection sized for the theoretical peak demand is therefore often substantially oversized, and more expensive (both in terms of grid connection and transformer/cable capacity).
How dynamic load balancing solves this
IEC 61851-1 defines, for Mode 3 charging (AC charging with communication), a Control Pilot (CP) signal between the charge point and the vehicle, through which the charge point communicates the maximum permitted charging current to the vehicle via duty-cycle modulation. A group-level load balancing system uses this by:
- Reserving a fixed, predetermined group power budget for the entire charging hub (for example 60 kW for the ten charge points in the example above, instead of 110 kW).
- Distributing this group power budget in real time across the vehicles currently charging, by continuously adjusting the CP signal for each charge point to the actual available capacity.
- Automatically recalculating the distribution whenever vehicles arrive or leave, so that the total group current never exceeds the reserved group capacity, not even momentarily.
Note: dynamic load balancing is an addition to, not a replacement of, the regular installation requirements from the 722-ev-charging guide — the RCD selection, earthing system and cable sizing per charge point remain fully applicable; load balancing only limits the simultaneous sum of charging currents at group level.
What goes wrong without load balancing
Without a load balancing system, the installation must be sized for the sum of all charge points at full power, or part of the charge points must be manually set to a lower, fixed power (with the drawback that this capacity also remains unused when only a few vehicles are charging simultaneously). An installation sized for the full peak demand without load balancing is functionally correct but economically inefficient; an installation connected at a lower, static power without load balancing risks overloading the main connection as soon as multiple vehicles charge simultaneously at full power.
Practical relevance
When designing a charging hub with multiple charge points, it must be established whether the connection capacity is sized for the theoretical peak demand (sum of all charge points) or for a lower, dynamically distributed group power budget — and in the latter case, it must be verified that the load balancing system never actually exceeds the group capacity, not even while individual vehicles connect or disconnect.
Common mistakes
- Treating load balancing as a replacement for the individual charge point requirements (RCD, earthing, cable cross-section per charge point) — these requirements from the 722-ev-charging guide remain fully applicable; load balancing operates at group level, not at charge point level.
- Setting a fixed, static power per charge point instead of dynamic distribution, and calling this "load balancing" — a static distribution does not optimally use the available group capacity and is not a full substitute for a system that redistributes in real time.
- Basing the group capacity on an optimistic assumption of simultaneity without accounting for peak moments (for example all vehicles arriving around the same time) — the chosen group capacity must also remain sufficient for an acceptable charging speed under a realistic worst-case scenario.
Related
Further reading
- §722Electric Vehicle (EV) Charging Points
- IEC 60364-5-53RCD selectivity — Type S and cascading residual current devices
- IEC 62020Residual current monitoring (RCM) versus RCD — continuous measurement instead of tripping
- §411Automatic Power Off (AUV)
- §702Swimming pools and fountains (§702) — zones, SELV and supplementary bonding
- §709Marinas and berths (§709) — individual RCD protection and galvanic corrosion