NEN 3140 §6.4

Test Sequence (NEN 3140 Inspection)

Beproevingsvolgorde (NEN 3140-inspectie)

The fixed, prescribed order in which the different steps of a periodic NEN 3140 inspection are carried out: first a visual inspection (visible damage, rating-plate data, fixing), then measurements in the de-energised state (continuity of protective conductors, insulation resistance, polarity), and only after that, where applicable, functional testing under voltage (including an RCD test). This sequence is not arbitrary: a visual inspection can reveal visible defects that would make energising the installation unsafe, and insulation-resistance measurement must always be performed before applying voltage to avoid damaging sensitive equipment. Skipping or reversing steps undermines the reliability of the inspection report.

Practical example

Tijdens een NEN 3140-inspectie van een verdeelkast merkt de inspecteur tijdens de visuele inspectie een gesmolten wandcontactdoos op; hij voert daarom geen isolatieweerstandsmeting of functionele test op die groep uit voordat het euvel is verholpen, conform de voorgeschreven beproevingsvolgorde.

Common mistake

Direct een RCD-test uitvoeren zonder eerst de continuïteit van de beschermingsleiding en de isolatieweerstand te controleren — als de PE-doorverbinding al onderbroken is, kan een RCD-test een schijnbaar goed resultaat geven terwijl de installatie in werkelijkheid onveilig is.

See also

Beschikbaar in: English, Nederlands, Polski, Русский, Українська
Test Sequence (NEN 3140 Inspection) — dictionary · NEN-Hub