Large-consumer connections — indirect metering via current transformers

Available in: en, nl, pl, ru, ua
Updated: ≈ 3 min read

Large-consumer connections — indirect metering via current transformers

A horticultural business with assimilation lighting, climate installations and its own CHP generation (see the CHP grid connection guide) often has a connection that lies far above the threshold of a regular "small-consumer" connection. From a certain connection capacity onward, not only the tariff and market model changes, but also the way of metering itself.

The threshold: greater than 3×80A

Connections larger than 3×80A fall under "large consumer" in the Netherlands and, unlike small-consumer connections, are not metered directly. Instead, the electricity meter is connected indirectly via current transformers (CTs): the main current does not flow through the meter itself, but through the primary winding of the CTs, which pass a reduced, proportional secondary current to the meter.

Why indirect metering is needed

For large-consumer connections, the currents are too large to run practically and safely straight through a meter (both in terms of the meter's construction and safety during replacement/maintenance). Current transformers make it possible to reduce a large primary current to a standard secondary value (often 1A or 5A) that a regular meter can process safely and accurately.

Accuracy class

The current transformers applied must, in terms of accuracy class, match the requirements of the main connection: the combination of CT and meter must deliver a reliable, verifiable measurement across the full expected load range of the connection. The specific requirements for CTs (accuracy class, transformation ratio, load capacity) and for the indirect metering setup as a whole are laid down by Netbeheer Nederland in the Meetcode Elektriciteit.

Note: the precise transformation ratio and accuracy class per CT follow from the design of the specific connection (by the grid operator/metering-responsible party) — this article gives the principle, not a universal figure that applies to every connection.

Practical consequence for the installation owner

  • The metering equipment (CTs + meter) is installed/managed by the metering-responsible party (often the grid operator or a recognised metering service), not at the discretion of the installation owner.
  • On extension or modification of the connection (for example by adding own generation such as CHP or battery storage), the metering setup must be reassessed — a CT that was correctly sized for the old situation may no longer be so for a new load or feed-back situation.

Common mistakes

  1. Assuming that a large-consumer meter is "just a bigger version" of a small-consumer meter — the indirect metering setup with CTs is fundamentally different in design from a direct meter.
  2. Intervening in or replacing CTs/metering equipment oneself without involving the metering-responsible party — this falls outside the authority of the installation owner and can jeopardise metering accuracy/legality.
  3. Failing to have the existing CT setup checked, in the case of own generation (CHP, battery storage), for whether it still correctly measures the changed (bidirectional) current profile.