Earthing and short-circuiting sets — periodic testing per IEC 61230
Earthing and short-circuiting sets — periodic testing per IEC 61230
The guide on the 5 safety rules covers when and why step 4 — earthing and short-circuiting — is applied when de-energizing an installation. This article covers a prior condition that is often skipped: is the earthing and short-circuiting set itself still reliable at the moment of use? IEC 61230 ("Live working — Portable equipment for earthing or earthing and short-circuiting") describes both the type test and the guidelines for periodic in-service checking of this set.
Why the set itself needs periodic checking
An earthing and short-circuiting set is the last barrier between the technician and an unexpected re-energization or induced voltage while working on a de-energized installation. If the set itself has an elevated transition resistance — due to corrosion, a loosened clamp contact, or damaged conductor strands — it may be unable to carry enough current during an actual fault, with the risk that part of that current still flows to earth through the technician. A set that looks visually intact therefore does not automatically guarantee a sufficiently low transition resistance.
Visual check before every use
Before every use, the complete set should undergo a visual check:
- Clamps: check for corrosion, deformation or hairline cracks in the clamp body, and for a firm, complete bite on the conductor or rail being connected.
- Conductor: check for broken strands, mechanical damage to the insulation, or oxidation at the clamp connection points — that is precisely where transition resistance first develops.
- Completeness of the set: verify that all components (earth, phase, and any neutral clamp) are present and belong to the same, matched set — an improvised set assembled from loose parts of different sets has never been tested as a whole.
Periodic resistance measurement: clamp-to-clamp
Besides the visual check, IEC 61230 provides for a periodic, instrumented check: measuring the electrical resistance between the clamps, through the full conductor and both clamp connections.
Note: IEC 61230 does not set a fixed maximum resistance value that applies to every set. Instead, the measured value is compared against the reference value recorded when that specific set was first put into service. A significant increase relative to that reference value indicates corrosion, a loosened contact, or the onset of strand breakage in the conductor, even if the set still looks fully intact visually.
In practice, this means every earthing and short-circuiting set needs a recorded baseline measurement at first commissioning, without which a later periodic measurement provides no meaningful comparison.
Sizing: cross-section matched to the prospective fault current
An earthing and short-circuiting set must be able to carry the installation's prospective fault current for the clearance time of the upstream protection device (typically on the order of 1 second) without melting or overheating unacceptably. A set that is oversized for a smaller installation than where it is currently deployed can physically fail during an actual fault before the upstream protection has cleared — the cross-section of the set must therefore match the actual prospective fault current at the point of use, not a generic rule of thumb.
Storage: just as decisive as the test itself
A correctly tested set that is then stored incorrectly — kinked, with a clamp dragging on the floor, or put away damp — can still develop an elevated resistance or damaged insulation by the next use, despite a recent, valid test date. Storing it dry, unkinked, and protected from mechanical damage is therefore just as decisive a factor in the set's reliability as the periodic test itself.
Practical relevance
When putting together a permit to work for de-energized work where step 4 of the 5 safety rules applies, it is important to check not just that an earthing and short-circuiting set is present, but also that that specific set has a valid, traceable periodic test date and a cross-section matched to the prospective fault current of the installation it is being applied to.
Common mistakes
- Using an earthing and short-circuiting set without a recorded baseline resistance at first commissioning, so a later periodic measurement provides no meaningful comparison.
- Deploying a set with too small a cross-section relative to the prospective fault current at the point of use, risking physical failure during an actual fault.
- Combining parts from different sets into an improvised assembly that has never been tested or certified as such.
- Storing a set incorrectly (kinked, damp, unprotected), which can undermine reliability despite a recent test date.
Related
Further reading
- IEC 60855 (isolerende stangen)Insulating rods and switching sticks — periodic testing per IEC 60855
- IEC 61508 (proof test)Safety relays and safety PLCs — periodic proof testing per IEC 61508
- InspectiePeriodic inspection according to NEN 3140
- IEC 62353IEC 62353 — periodic testing of medical electrical equipment
- ExamenCalculation questions — short-circuit current & voltage drop
- InspectieTesting the RCD — trip time and residual current (NEN-EN-IEC 61557-6)